Question Q-19GS3GS3

Despite the government's ambitious targets, rooftop solar installations in India are hindered by multiple factors. Elaborate. How far do you think that PM Suryaghar Yojana can incentivise the adoption of top solar installations?

Open scan (p.29)

Introduction

Out of the total installed solar capacity

7 words

Main Body

Out of the total installed solar capacity of ~ 82 GW, roughly 67 GW is large solar and ~ 15 GW is rooftop installed, while the target was of 40 GW rooftop by 2022. Factors behind poor adoption: (1) Political factors: Different regulations in different states hindering adoption e.g. Haryana & Gujarat pro-rooftop (2) Social attitudes toward rooftop: Lack of awareness on subsidies, pricing, etc. (3) Economic cost of installation high - Upto ₹ 2 lakh for installation

4Environmental: Shortened life of solar panels due to increasing temperatures (5) Geopolitical factors: Import dependence on China for solar cells and associated price rise due to conflict Potential of PM Suryaghar Yojana: (1) Free installation will increase adoption - Already over 3 million registrations (2) Facility of supplying excess to grid will provide income source to users (3) Govt approved players will ensure trust on suppliers (4) Govt push will promote R&D leading to more efficient & cheaper solar cells
5Will bring investment and help reduce dependence on China - Release setting up manufacturing in Jamnapar Challenges in urban bids in scheme: - Cost of MRO on users - Potential inclusion-exclusion errors - Lack of skilled installation workers - threat of disasters like fire/electrocution in Hissar, Haryana
207 words1 paragraphs

Conclusion

To overcome above challenges, standard universal SOPs need to be circulated and training modules may be made available

18 words

Answer continues on next page

Topper

BHAVESH JAGLAN

AIR 1282025

Subject & Paper

GS3GS3

Topic

Science and Technology

Solar Energy

Rooftop solar installations and policy incentives