Question 3GS3GS3
To what extent was the first National Monetization Pipeline (NMP) able to meet its objectives? What are the objectives of the new Asset Monetization Plan 2025-30 as announced in the recent 2025 Budget?
Main Body
3. Helped in adding value to the stranded legacy infrastructure. 3.1 - Brown field projects 3.2 - Green and Play project New AMP 2025-30 includes: 1. Existing Digital Bank - Two Lenders KOI based allocation and tracking utilization 2. Land + Model - Land act to Privatise - Incentives like Soft loans 3. Geospatial - Remote sensing and GPS based tracking 4. PPP Projects - Better control over project - Risk distribution 5. Cycle mechanism of monetization - based on quality of asset
83 words1 paragraphs