2014 · Q11
15 men complete a work in 16 days. If 24 men are employed, then the time required to complete that work will be
Elementary MathematicsArithmetic
- A7 days
- B8 days
- C10 days
- D12 days
Explanation
15 x 16 = 24 x d gives d = 10 days.
15 men complete a work in 16 days. If 24 men are employed, then the time required to complete that work will be
Explanation
15 x 16 = 24 x d gives d = 10 days.